Frederick Goethals.← Back to selected work
Case 02 / Active project analysis

Budget Variance and Reforecasting Report

A live capital-budget view that reconciles the original plan, approved revisions, forecast-at-completion, and draw activity by scope.

$1.30MFinal forecast
+19.9%Change from original
99.1%Capital funded
$11.7KBalance remaining
Selected model views

Inside the model.

The report makes it possible to see the project’s current capital position without reading through the source draw package: the overall variance, the scopes driving it, deployment progress, and the remaining completion exposure.

Illustrative portfolio example. Property, client, and source identifiers have been removed.

Discuss a similar project